4  Work Planning

Annual Progress Report

The Lower Nicola Indian Band, Nooaitch Band, and Scw’exmx Tribal Council completed in-depth barrier assessments and habitat confirmations at several sites (Stumbles, Kwinshatin, Brook, Murray Lake, Midday creeks). In addition, initial results from CWF’s drone imagery project to identify thermal refugia were developed and reviewed at a working group meeting with program partners in 2023.

Annual Work Plan

Table 4.1:

2023 work plan for the Lower Nicola Watershed.

Task

Lead for Next Step

Participants

Timeline

Notes

Review 2023 and prior field results with WG and advance/reject crossings based on outcomes

CWF

WG

June (2024)

Review lateral habitat report with partners working on lateral habitat identification in watershed to refine methods

CWF

Nooaitch, NVIT

June-August 2024

Meet with partners to get feedback on potential for CWF to take a coordination role on thermal refugia habitat mapping, identification and prioritization & identify data gaps; begin coordinating (depending on feedback)

CWF

WG

June-October 2024

Requires feedback from working group

Complete barrier removal on Clapperton Creek

CWF

LNIB

July (2024)

Complete barrier assessments for next set of crossings

CWF

LNIB, Nooaitch, STC

August (2024)

Complete habitat confirmation on Manning Creek

CWF

LNIB, Nooaitch, STC

August (2024)

Update model with all current relvant information for Lower Nicola watershed

CWF

WG

December of 2024

Review 2024 assessment results with working group

CWF

WG

January-February 2025

Re-run connectivity models

CWF

February-March 2025

Develop 2025-2026 work plan

CWF

WG

February-March 2025

Update WCRP based on 2024 field results and partner feedback

CWF

WG

March-April 2025

Operational Plan

The operational plan represents a preliminary exercise undertaken by the planning team to identify the potential leads, potential participants, and estimated cost for the implementation of each action in the Lower Nicola River watershed. Table 2 summarizes individuals, groups, or organizations that the planning team felt could lead or participate in the implementation of the plan and should be interpreted as the first step in ongoing planning and engagement to develop more detailed and sophisticated action plans for each entry in the table. The individuals, groups, and organizations listed under the “Lead(s)”, or “Potential Participants” columns are those that provisionally expressed interest in participating in one of those roles or were suggested by the planning team for further engagement (denoted in bold), for those that are not members of the planning team. The leads, participants, and estimated costs in the operational plan are not binding nor an official commitment of resources; but rather provide a roadmap for future coordination and engagement during the WCRP implementation.

2023 operational plan for the Lower Nicola Watershed.

Strategy / Actions

Lead(s)

Participants

Total Budget

Strategy 1: Crossing Rehabilitation

$4,038,000.00

1.1 – Rehabilitate dykes and berms

CWF, Scw’exmx Tribal Council (STC)

Upper Nicola Band, Lower Nicola Indian Band, Nooaitch Band, Shackan Indian Band, Stuwix Resources Joint Venture (SRJV), Coldwater Band, Cooks Ferry Band, Trout Unlimited, Fisheries and Oceans Canada (DFO)

$3,600,000.00

1.2 – Reconnect channels to thermal refugia

CWF, STC

Upper Nicola Band, Lower Nicola Indian Band, Nooaitch Band, Shackan Indian Band, SRJV, Coldwater Band, Cooks Ferry Band, Trout Unlimited, DFO

$288,000.00

1.3 – Knowledge Gap: Improve mapping of lateral habitat and thermal refugia

Tom Willms

CWF, Fraser Basin Council

$50,000.00

1.4 - Knowledge Gap: Revisit previous rehabilitation and off-channel habitat creation projects to assess whether they are still fish-passable

STC

CWF, Mark Gaboury, DFO, Tom Willms

$100,000.00

1.5 - Review LiDAR, aerial imagery, and field assessments to determine immediate lateral connectivity needs.

Strategy 2: Lateral Barrier Rehabilitation

$12,986,140.00

2.1 – Remove and decommission barriers

CWF, STC

Upper Nicola Band, Lower Nicola Indian Band, Nooaitch Band, Shackan Indian Band, SRJV, Coldwater Band, Cooks Ferry Band, DFO

$1,008,000.00

2.2 – Upgrade and resize crossings

CWF, STC, Ministry of Transportation and Infrastructure

Upper Nicola Band, Lower Nicola Indian Band, Nooaitch Band, Shackan Indian Band, SRJV, Coldwater Band, Cooks Ferry Band, DFO

$10,962,000.00

2.3 – Install and maintain temporary mitigation

CWF

Upper Nicola Band, Lower Nicola Indian Band, Nooaitch Band, Shackan Indian Band, SRJV, Coldwater Band, Cooks Ferry Band, DFO

$630,000.00

2.4 – Initiate a barrier owner outreach program

TBD

CWF, Nicola Watershed Community Round Table, Nicola Stockbreeders Association

$100,000.00

2.5 – Request regulatory action for non-compliant crossings

TBD

CWF, DFO (C&P)

$10,000.00

2.6 – Knowledge Gap: Identify barriers and map barrier ownership

Fraser Basin Council (FBC)

CWF, SRJV, Provincial government

$100,000.00

2.7 – Knowledge Gap: Continue updating the structure prioritization model

CWF

TBD

$100,000.00

2.8 – Knowledge Gap: Adapt the provincial fish passage framework to account for ephemeral habitat

CWF

TBD

TBD

2.9 – Knowledge Gap: Assess barriers by applying an adapted version of the provincial fish passage framework

CWF

STC, DFO

$76,140.00

Strategy 3: Dam Rehabilitation

TBD

3.1 - Remove dams

TBD

TBD

TBD

3.2 - Install fish passage

TBD

TBD

TBD

3.3 - Knowledge Gap: Continue updating the structure prioritization model

CWF

TBD

$0.00

3.4 - Knowledge Gap: Assess dams to determine whether they exist and are truly blocking fish habitat

TBD

TBD

TBD

3.5 - Knowledge Gap: Identify and map dam ownership

TBD

TBD

TBD

Strategy 4: Barrier Prevention

TBD

4.1 – Work with land users to improve their aquatic connectivity practices

TBD

TBD

TBD

4.2 – Monitor new crossing compliance with regulations regarding fish passage

TBD

TBD

TBD

Strategy 5: Progress Tracking Plan

TBD

5.1 - Engage and explore integration with existing regional initiatives

CWF, Nicola Watershed Governance Project, FBC

TBD

TBD

5.2 - Implement the WCRP Progress Tracking Plan

CWF

TBD

TBD

Total:

$17,024,140.00

Fundraising total:

$9,024,140

Proponent/government contribution total:

$8,000,000